Scheduled to begin Tuesday, August 20, 2019, is reconstruction of the downtown area traffic signals and construction of pedestrian nodes. The project will increase safety for pedestrians and bicyclists, and provide driver’s additional sight enhancements.
The project intersection locations are:
- 11th Street and 23rd Avenue
- 13th Street and 23rd Avenue
- 13th Street and 25th Avenue
- 13th Street and 26th Avenue
- 13th Street and 27th Avenue
- 14th Street and 23rd Avenue
- 14th Street and 26th Avenue
- 15th Street and 23rd Avenue
- 15th Street and 26th Avenue
- 17th Street and 23rd Avenue
During construction, there may be periods of time where temporary stop signs are placed and driving lane widths are reduced. Construction will continue until winter and, pending the timing of winter construction shut down, may need to be completed in spring 2020.